ProEnergy Braes Bayou Gas Turbine Peaking Plant – Texas

circle-thick-red

Braes Bayou 8 x LM6000

PPS Services Group provided the detailed  design engineering as part of an EPC team with  ProEnergy for a 400 MW simple cycle power plant  utilizing eight General Electric LM6000 combustion  turbine generators. Natural Gas is delivered  to the site at conditions suitable for the CTG’s.

The Project included a 13.8kv to 345kv Substation using four (4) three-winding Generator Step-Up Transformers in parallel. The substation will  interconnect with Centerpoint Energy.