Location:
Brazoria County, TX
Brotman Generating Station
8 x LM6000 Installation
PPS Services Group provided the detailed design engineering as part of an EPC team with ProEnergy for the installation of eight General Electric LM6000 combustion turbine generators. The plant will be used as a peaking plant to supplement the wind and solar power production.
The Project included a 138kv Electrical Switchyard which ties-in to the existing substation.