ProEnergy Mark One Gas Turbine Peaking Project – Texas

circle-thick-red

Mark One Generating Station
10 x LM6000 Installation

PPS Services Group provided the detailed  design engineering as part of an EPC team with  ProEnergy for the installation of ten General Electric  LM6000 combustion turbine generators. The plant will be used as a peaking plant to supplement the  wind and solar power production.

The Project included a 138kv Electrical Switchyard  which ties-in to the  existing substation. The Project is a fast-track  project, being engineered, procured, and  constructed in less than 6 months to meet summer peak demands.